首頁 > 行業(yè)資訊

中國能建提前完成臺山核電2汽機扣蓋

來源:新能源網
時間:2014-08-07 18:56:24
熱度:

中國能建提前完成臺山核電2汽機扣蓋.TRS_Editor P{margin-top:1em;margin-bottom:1em;line-height:2;font-family:

.TRS_Editor P{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor DIV{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor TD{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor TH{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor SPAN{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor FONT{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor UL{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor LI{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}.TRS_Editor A{margin-top:1em;margin-bottom:1em;line-height:2;font-family:宋體;font-size:10.5pt;}

  8月5日,中國能源建設集團有限公司所屬廣東火電工程總公司承建的臺山核電項目2號機組常規(guī)島汽機扣蓋一次成功,比原計劃提前10天。

  當日上午8時,中國能建廣東火電項目部員工進行安全技術交底后有條不紊地開展各項工作,并于當天下午5時50分高質量地完成2號機組汽機扣蓋,比計劃提前10天,獲得業(yè)主的充分肯定。

  臺山核電項目是我國首個175萬千瓦核電項目,一期工程機組是基于第三代核電EPR(歐洲壓水堆)技術的CEPR(中國的EPR)技術機組,也是世界單機組容量最大的核電機組,核電汽輪機安裝精度要求極高。臺山核電2號機組項目于2010年4月開工建設,從2013年11月臺山核電2號機組3個低壓缸全部就位結束,到低壓缸(LP3汽缸)扣蓋一次成功,歷經10個月。